5.3 Managementul schimbarii/ Breviar

5.3.P1 Livrabile:

Urmatoarele livrabile sunt disponibile in bibliotecile de sabloane TenStep care sustin acest proces.  (unele dintre sabloan pot fi accesate doar de membrii inregistrati.)

  • Formular de cerere a schimbarii de continut
  • Jurnalul de schimbari ale continutului

5.3.P2 Activitatile din planificare

Marime

Informatii Necesare

Mici

Proiectele mici nu au nevoie de pasi specifici in planificare pentru managementul continutului. Totusi, dupa revederea activitatilor pentru proiecte mari, puteti adauga articole aditionale la planificare daca trebuie.

Medii

Activitate

Efort

Comentarii

Revizia stadiului cererilor de schimbare

1-2 ore

Weekly. Always assigned to the project manager. Use this time to ensure progress is being made on all scope change requests and that the Scope Change Log is updated. 

Analiza cererilor de schimbare

Deschis

Add an activity for the analysis of any open scope change requests that were assigned to a team member.

Rezolvarea cererii de schimbare

Deschis

If the resolution of a scope change request requires additional work activities, the activities should be added to the project schedule.


Mari

Activitate

Efort

Comentarii

Revizia stadiului cererilor de schimbare

1-2 ore

Weekly. Always assigned to the project manager. Use this time to ensure progress is being made on all scope change requests and that the Scope Change Log is updated. 

Analiza cererilor de schimbare

Deschis

Add an activity for the analysis of any open scope change requests that were assigned to a team member.

Rezolvarea cererii de schimbare

Deschis

If the resolution of a scope change request requires additional work activities, the activities should be added to the project schedule.

Carta actualizarilor proiectului

Deschis

Add an activity to update the Project Charter to reflect any major approved scope change requests or if a number of small approved changes make the scope section of the current Project Charter invalid.